Today we ripped out the last of the previous construction company's offenses. The subgrade of the large practice putting green; about 1000 square meters in size. Like the 3rd, it was built primarily of topsoil and had chunks of wood in it.

We trucked the topsoil to the range for capping the clay. We will have to run the cultivator lightly over the range, followed by the spike harrow, and have a small army of guys following... picking out the offensive extras for at least a day.

The range is 90% capped in topsoil, and the remainder of capping material should be in place late this evening. Only a bulldozer has to spread it out... and just in time. It started raining today.