Tuesday, October 30, 2007

15 Tees Cored and Filled

On to 15 tees the topsoil has been removed and the sand from the quarry on 12 driven in to build their foundation. Now we have to compact the material, stake the form and bring the subgrade to the desired slope and elevation.

From here the subgrade is smoothed out with the bunker rake,irrigation installed and rootzone (mix of sand and soil the grasses will grow in)installed, smoothed out and the outer areas tied into the tee area so everything flows together. It sounds easy, but each step requires work and attention to detail.